Project Management Professional Practice Question

During a system-upgrade project, the team discovers that production servers cannot be patched until the procurement department signs a new software license agreement-an activity outside the team's authority. According to PMP People domain Task 7, what should the project manager do FIRST to remove this impediment?

  • Encourage the project team to handle and remove every impediment on their own, without outside assistance.

  • Postpone the work until the weekly status meeting so the sponsor can decide how to proceed.

  • Add the item to the risk register and move on to other tasks until procurement resolves it themselves.

  • Leverage the project manager's organizational network to engage the procurement manager and obtain the needed approval.

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot