Project Management Professional Practice Question

During a sprint review, the product sponsor asks the Scrum team why they insist on releasing a small, potentially shippable slice of the product every few weeks instead of waiting for a single large release at the end of the project. Which outcome represents the primary benefit of delivering work iteratively and incrementally in an agile environment?

  • It postpones system integration and testing until the last iteration, reducing overhead during early sprints.

  • It maximises opportunities for inspection and stakeholder feedback, allowing the team to adjust the product to real customer needs while work is still under way.

  • It locks the scope early, enabling the team to generate a detailed schedule that remains stable for the rest of the project.

  • It guarantees that team velocity will remain constant because each iteration contains an identical amount of effort.

Project Management Professional
Agile
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot