PMI Project Management Professional Practice Question

During a software development project, the project manager is collaborating with the client and the development team to determine how best to implement new features that will increase market share and customer satisfaction. The project is complex and involves several interdependent modules. What would be the most effective approach to managing the delivery of these features?

  • Focus primarily on back-end development initially as it's the most complex part, releasing the front-end elements in later stages.

  • Subdivide the project into smaller, incrementally deliverable modules that provide functioning segments of the software to garner early and frequent feedback from the client.

  • Begin by launching the least complex features to the market to establish presence and gradually scale up with more features.

  • Develop the entire software in one-go to ensure all elements are compatible and then present it to the client for feedback.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot