PMI Project Management Professional Practice Question

During a software development project, the project manager decides to adopt an iterative approach to incorporate lessons learned into the project life cycle. After each development sprint, which of the following activities should primarily be conducted to best utilize the iterative, incremental practices?

  • Revising the project's communication plan to include additional stakeholders

  • Holding a retrospective meeting to discuss the outcomes of the sprint and areas for improvement

  • Conducting a mid-project external audit to assess compliance with industry standards

  • Updating the risk management plan to include new potential risks

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot