PMI Project Management Professional Practice Question

During a project status review, a project manager realizes that the tasks are running behind the original timelines. Given the importance of aligning with previously successful projects' benchmarks, which of the following actions would be BEST to perform next?

  • Revise the project schedule including adjustments based on historical data from similar past projects.

  • Introduce longer working hours to catch up with the delay.

  • Conduct an immediate team meeting to discuss delays.

  • Apply pressure to the team to speed up the work without revising any schedules.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot