PMI Project Management Professional Practice Question

During a project status meeting, a project manager determines that the Earned Value (EV) is $300,000, the Actual Cost (AC) is $350,000, and the Planned Value (PV) is $250,000. What is the Cost Performance Index (CPI) for the project, and what does it signify about the project's cost efficiency?

  • 1.2, indicating that the project is under budget and cost-efficient

  • 0.86, indicating that the project is over budget and not cost-efficient

  • 0.75, indicating that the project has a favorable cost variance

  • 1.0, indicating that the project is right on budget

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot