Project Management Professional Practice Question

During a project meeting, you notice two team members, Sarah and John, are visibly frustrated. Sarah is concerned about the project's direction, feeling it isn't aligned with initial expectations. John, on the other hand, expresses concerns about the timeline being too aggressive. As the project manager, how can you best interpret the source and stage of this conflict?

  • You selected this option

    The conflict stems from external stakeholders and is in the negotiation stage.

  • You selected this option

    The conflict is task-related and at the disagreement stage.

  • You selected this option

    The conflict is personal and at the deadlock stage.

  • You selected this option

    The conflict is process-related and has escalated to a crisis.

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot