PMI Project Management Professional Practice Question
During a project kickoff meeting, the project manager discusses the day-to-day work expectations to align the new team members. Which of following best reflects proper outlining of expectations for the working environment?
Encourage team members to work the hours that suit them best, as long as the work is completed.
Advise the team to send detailed emails for documentation purposes weekly.
Recommend frequent coffee breaks to promote informal discussions and relaxation.
Mention that all team members are expected to use specific collaboration tools for project communication and task management.