Project Management Professional Practice Question

During a project kickoff for a cross-functional team, the project manager has each member complete a recognized personality indicator (such as DiSC or MBTI) and privately reviews the consolidated results. What is the principal reason the project manager performs this activity as part of promoting team performance under PMI's expectations?

  • To categorize team members into fixed roles based on their personality types

  • To understand the emotional needs and preferences of stakeholders and adapt leadership and communication approaches accordingly

  • To predict with certainty which personality types will cause conflicts on the project

  • To single out team members who should be removed from the project

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot