During a mid-project risk review workshop on a 12-month agile-hybrid software project, the project manager and core team are examining the updated risk register to decide which of the 30 identified threats must be addressed in the next two-week sprint. The sponsor emphasizes that any risk likely to affect the forthcoming product increment within the next fortnight must be tackled first. According to PMI's Perform Qualitative Risk Analysis guidelines, which tool or technique should the team apply to rank the threats by the speed with which responses must be implemented?

  • Risk Urgency Assessment

  • Risk Categorization

  • Monte Carlo Simulation

  • Expert Judgment

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot