Project Management Professional Practice Question

During a large, multi-phase software development project, the project manager decided to implement a structured approach for knowledge transfer between the departing and incoming team members. What is the best method to confirm that the knowledge transfer approach is effective, thus ensuring continuity for the subsequent project phase?

  • Introduce new collaboration tools designed to facilitate information sharing.

  • Schedule regular review sessions between the departing and incoming team members, along with stakeholders, to evaluate the transfer process.

  • Distribute surveys to incoming team members to independently assess their understanding of the project details.

  • Organize comprehensive training events that cover all aspects of the project phases completed so far.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot