Project Management Professional Practice Question

During a large construction project, a risk materializes into an issue. The project manager determines the resulting delay will exceed the contingency time allocated in the project schedule. What is the most appropriate next step for the project manager?

  • Discuss the issue informally with project managers from other departments.

  • Wait to see if the situation resolves itself before taking further action.

  • Schedule a meeting with the project team to brainstorm potential solutions.

  • Escalate the issue to higher management for strategic guidance and support.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot