Project Management Professional Practice Question

As the project manager for a software development project, you identify that your team of developers prefers detailed technical discussions, while your investors are interested in high-level progress updates. How should you address the different communication requirements to ensure that the needs of both stakeholders are met effectively?

  • Eliminate routine updates to the investors and only communicate with them if there is a problem that threatens the project timelines or budget.

  • Send detailed technical updates to all stakeholders, including both developers and investors, to maintain transparency and keep everyone equally informed.

  • Create separate communication plans for the developers and investors, ensuring that each group receives information that is relevant and at the appropriate level of detail for them.

  • Focus only on high-level progress updates in all communications to avoid getting bogged down in technical details.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot