As a project manager, you recognize the importance of maintaining accessible and current project artifacts to support informed decision-making. Which of the following actions would best ensure the continual effectiveness of artifact management?
Wait for team members or stakeholders to request updates to project artifacts before making any changes.
Update project artifacts when major project milestones are reached or when significant changes occur.
Use an automated version control system notifications to alert stakeholders when artifacts have been updated.
Conduct regularly scheduled reviews of project artifacts with relevant stakeholders to discuss updates and collect feedback.