Project Management Professional Practice Question

As a project manager, you notice that your team's progress has slowed down significantly due to a lack of timely responses from a key stakeholder, including an attempt to meet one-on-one with the stakeholder. Which of the following actions should you take to address this impediment?

  • Continue waiting for the stakeholder's response without taking any action

  • Adjust the project timeline to accommodate the delay caused by the stakeholder's lack of response

  • Assign additional tasks to the team to compensate for the delay

  • Escalate the issue to the project sponsor or higher management to help resolve the problem

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot