PMI Project Management Professional Practice Question

As a project manager, you have noticed that one of your team members, who is a subject matter expert, has a significant influence over the rest of the team. However, this team member is resistant to a critical change in the project scope. What is the best approach to handle this situation?

  • Impose the change in the project scope without addressing the team member's concerns, as the project objectives take precedence.

  • Schedule a one-on-one meeting with the influential team member to understand their concerns and find a mutually agreeable solution.

  • Escalate the issue to higher management and request them to intervene and enforce the change in project scope.

  • Ignore the team member's influence and resistance, and focus on gaining support from other stakeholders.

PMI Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot