As a project manager, you have identified several impediments affecting your team's performance. Which of the following factors should be considered first when prioritizing these issues?
The effect of the impediment on team morale
The availability of resources to tackle the impediment
The impact of the impediment on project objectives
The complexity of the solution required to address the impediment
The impact on project objectives should be the primary consideration when prioritizing impediments, obstacles, and blockers. Issues that directly affect the project's scope, timeline, budget, or quality should be addressed first, as they can have the most significant consequences on project success. While the other factors mentioned (team morale, resource availability, and complexity of the solution) are important, they should be considered secondary to the direct impact on project objectives.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are project objectives, and why are they important in prioritizing impediments?
Open an interactive chat with Bash
How can project managers identify the impact of an impediment on project objectives?
Open an interactive chat with Bash
What other factors should project managers consider after assessing the impact on project objectives?
Open an interactive chat with Bash
Project Management Professional
People
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access