Project Management Professional Practice Question

As a project manager, you have conducted a training session for your team on a new software tool that will be used in the upcoming project. Which of the following is the most effective way to measure the training outcomes?

  • Rely on team members' self-assessment of their ability to use the software tool effectively

  • Ask team members to provide verbal feedback on their confidence in using the software tool

  • Conduct a practical assessment that requires team members to demonstrate their proficiency in using the software tool

  • Conduct a written test to assess the team's understanding of the software tool

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot