Free PMI Project Management Professional Practice Question

As a project manager, you are tasked with engaging a group of stakeholders for a new construction project. Each stakeholder group has varying levels of influence and interest. What is the BEST way to engage these stakeholders to ensure the project’s success?

  • Send the same type of weekly project updates to all stakeholders.

  • Limit interaction with stakeholders to moments when critical issues arise.

  • Use formal reports as the method of communication for all stakeholder categories.

  • Develop a tailor-made engagement plan based on the influence and interest of each stakeholder group.

This question's topic:
PMI Project Management Professional / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.