Project Management Professional Practice Question

As a project manager in charge of a large-scale construction project, you are responsible for overseeing the management of project artifacts. To ensure their effectiveness, you decide to conduct regular assessments. Which of the following actions would be MOST effective in assessing the management of these artifacts?

  • Conduct structured audits of the artifact management processes

  • Review the last update dates of artifacts in project management software

  • Interview team members periodically about their satisfaction with artifact management

  • Ask for client feedback on the clarity and usefulness of project artifacts

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot