As a project manager for a software development project, you have identified a stakeholder who has previously worked on similar projects and has experience with the specific technology your project is employing. Given the need to effectively utilize individual stakeholder skills, what is the MOST appropriate way to involve this stakeholder in the project?
Recommend the stakeholder for a position outside the project to capitalize on their broader organizational experience.
Involve the stakeholder as a subject matter expert to provide technical guidance to the team.
Assign routine administrative tasks to the stakeholder to assist the project team.
Request the stakeholder to take up project management responsibilities to oversee the entire project.
Involving the stakeholder as a subject matter expert (SME) leverages their specific knowledge and prior experience, which can provide valuable insights to your project team. Providing technical guidance will help bridge gaps in understanding and enable the team to make well-informed decisions. Other options do not directly capitalize on the stakeholder's specialized skills to the same extent.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a Subject Matter Expert (SME)?
Open an interactive chat with Bash
How can I effectively engage a stakeholder as an SME?
Open an interactive chat with Bash
Why is it important to involve stakeholders with specific technology experience?
Open an interactive chat with Bash
Project Management Professional
People
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access