Project Management Professional Practice Question

A project manager is leading a software development project using an iterative approach. After the team successfully completes the second of five planned iterations, a key stakeholder suggests that all lessons learned activities be postponed until the end of the project to save time and streamline the current workflow. What is the project manager's most appropriate action?

  • Schedule a single, comprehensive lessons learned session midway through the project as a compromise.

  • Document the lessons learned from the current iteration privately but agree to postpone the team discussion until the project concludes.

  • Agree with the stakeholder to consolidate all lessons learned activities at the final project closure phase to maximize efficiency.

  • Politely explain to the stakeholder that lessons learned are captured after each iteration to allow for continuous improvement and adaptation throughout the project.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot