To determine the risk score, we multiply the probability by the impact for each risk:
Risk 1: 0.3 x 0.5 = 0.15 Risk 2: 0.6 x 0.2 = 0.12
The first risk has a score of 0.15, which is higher than the second risk's score of 0.12. This demonstrates that a risk with lower probability can still have a higher overall risk score if its impact is significantly higher. Understanding how to calculate and compare risk scores is crucial for prioritizing risks and developing appropriate response strategies in project management.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.