PMI Project Management Professional Practice Question

A project team is using an agile project management tool to track their work. Which of the following practices would BEST enhance transparency and facilitate the timely sharing of project information with all stakeholders?

  • Restrict viewing permissions in the tool to the core project team to reduce information overload for other stakeholders.

  • Focus on documenting detailed specifications rather than working software to keep all stakeholders uniformly informed.

  • Ensure all project artifacts are posted in a visible, shared space in the project management tool that is accessible to all stakeholders.

  • Use multiple specialized tools for different aspects of the project to ensure the most sophisticated feature set for each task.

PMI Project Management Professional
Agile
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot