Project Management Professional Practice Question

A project manager on a software development project noticed a decline in team velocity and an increase in bug reports over the past three sprints. To address this, the project manager facilitated a series of workshops on improved coding standards and provided new automated testing tools. Two sprints have now passed since these interventions were implemented, and the project manager needs to report on the effectiveness of these measures to senior management. What is the most appropriate next step for the project manager to take?

  • Conduct a team-wide survey to measure morale and satisfaction with the new tools and workshops.

  • Ask the product owner for their qualitative assessment of the recent deliverables' quality.

  • Schedule one-on-one meetings with each developer to gather their self-assessments of individual performance improvement.

  • Analyze the trends in team velocity and the number of defects reported per sprint, comparing the data from before and after the interventions.

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot