A project manager on a complex project diligently adds new impediments to the issue log as soon as they are identified by the team. However, once an impediment is logged, the project manager does not update the entry again until a team member confirms it has been completely resolved. What is the MOST significant risk of this management approach?

  • Stakeholders may not be aware of who is responsible for resolving the issues.

  • The progress on resolving open issues is not tracked, which could lead to unresolved impediments delaying the project.

  • New issues might be overlooked if the log is not reviewed frequently.

  • The final resolution of the impediment may not be properly documented for future lessons learned.

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot