Project Management Professional Practice Question

A project manager notices that the team is completing activities according to the detailed project schedule, yet some decisions made by team members do not advance the overall project objectives. Which of the following actions would BEST help the project manager align the team's day-to-day efforts with the project's goals?

  • Increase the frequency of earned value analysis to detect schedule and cost variances earlier.

  • Add additional interim milestones to the schedule to make progress checkpoints more frequent.

  • Facilitate a workshop to co-create and communicate a clear project vision and mission statement.

  • Apply a crashing technique to shorten activities on the critical path.

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot