Project Management Professional Practice Question

A project manager needs a visual artifact that follows the 100 % rule by decomposing the overall project deliverable into progressively smaller, manageable components so that all required work is captured. Which artifact should the project manager develop?

  • Work Breakdown Structure (WBS)

  • Milestone chart

  • Responsibility Assignment Matrix (RACI)

  • Product backlog

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot