Project Management Professional Practice Question

A project manager leading a software development project has just completed the initial stakeholder analysis, resulting in a stakeholder register that categorizes individuals using a power/interest grid. To effectively manage expectations and foster support for the project, what should the project manager do next?

  • Develop a stakeholder engagement strategy based on the analysis

  • Immediately execute engagement activities based on initial assumptions

  • Assign project responsibilities and tasks to key stakeholders

  • Begin sending regular project status updates to all stakeholders

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot