Project Management Professional Practice Question

A project manager leading a large construction project reviews work performance data and discovers significant schedule delays due to prolonged, unexpected severe weather. The current forecast indicates these conditions will continue, making the original schedule baseline unachievable. What is the project manager's best next step?

  • Inform the project sponsor that the deadline will be missed and ask for direction.

  • Analyze the impact of the delay on project objectives and submit a change request with corrective action options.

  • Immediately update the project schedule baseline to reflect the new, realistic completion date.

  • Use management reserves to fast-track the remaining activities and recover the schedule.

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot