A project manager is working on a software development project in the healthcare sector, which requires adherence to strict data protection regulations. The project manager needs to report on the project’s compliance status in the upcoming steering committee meeting. Which of the following would be the most effective method for measuring the project's compliance?
Conducting client satisfaction surveys focusing on data security.
Evaluating the need to expand original project deadlines.
Collecting general feedback on project performance from team members.
Using compliance metrics specific to healthcare data protection standards.