PMI Project Management Professional Practice Question
A project manager is working on a project that has shifted from a predominantly predictive approach to incorporating more agile practices. According to the PMI's Agile Practice Guide, what is a key factor the project manager should consider to increase the success of this transition?
Aligning the project practices with the organizational culture
Reducing the frequency of team meetings to allow more focused work
Eliminating customer collaboration to streamline decision-making
Increasing the level of documentation to ensure comprehensive coverage