PMI Project Management Professional Practice Question

A project manager is working on a project that has shifted from a predominantly predictive approach to incorporating more agile practices. According to the PMI's Agile Practice Guide, what is a key factor the project manager should consider to increase the success of this transition?

  • Aligning the project practices with the organizational culture

  • Reducing the frequency of team meetings to allow more focused work

  • Eliminating customer collaboration to streamline decision-making

  • Increasing the level of documentation to ensure comprehensive coverage

PMI Project Management Professional
Agile
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot