PMI Project Management Professional Practice Question

A project manager is working on a cost-plus incentive fee contract with the following parameters: Ceiling Price = $1,000,000, Target Price = $800,000, Buyer's Share Ratio = 80%, and Target Cost = $750,000. What is the Point of Total Assumption (PTA) for this contract?

  • $1,000,000

  • $962,500

  • $925,000

  • $950,000

PMI Project Management Professional
Process
Your Score:
Settings & Objectives

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot