A project manager is using Three-Point Estimation to calculate the expected duration of a critical activity. The optimistic estimate is 10 days, the most likely estimate is 14 days, and the pessimistic estimate is 22 days. What is the expected duration (TE) of this activity?
The correct answer is 14.67 days. In Three-Point Estimation, the expected duration (TE) is calculated using the formula: TE = (Optimistic + 4 x Most Likely + Pessimistic) / 6. Plugging in the values from the question:
TE = (10 + 4 x 14 + 22) / 6 TE = (10 + 56 + 22) / 6 TE = 88 / 6 TE = 14.67 days
This method gives more weight to the most likely estimate, providing a balanced approach to estimation that considers both best-case and worst-case scenarios. It's important to note that the result is often rounded to two decimal places in practice, but the exact calculation is provided here for clarity.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the Three-Point Estimation method?
Open an interactive chat with Bash
Why is the most likely estimate weighted more heavily in Three-Point Estimation?
Open an interactive chat with Bash
How does Three-Point Estimation reduce risk in project planning?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .