A project manager is using Three-Point Estimation to calculate the expected duration of an activity. The optimistic estimate is 10 days, the most likely estimate is 15 days, and the pessimistic estimate is 28 days. What is the expected duration (TE) of the activity?
17.67 days
16.33 days
18 days
15 days