Free PMI Project Management Professional Practice Question

A project manager is using Three-Point Estimation to calculate the expected duration of an activity. The optimistic estimate is 10 days, the most likely estimate is 15 days, and the pessimistic estimate is 28 days. What is the expected duration (TE) of the activity?

  • 17.67 days

  • 16.33 days

  • 18 days

  • 15 days

This question's topic:
PMI Project Management Professional / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.