PMI Project Management Professional Practice Question
A project manager is using the PERT technique to estimate the duration of a critical activity. The optimistic estimate is 10 days, and the pessimistic estimate is 22 days. What is the standard deviation for this activity?
2 days
4 days
3 days
1 day