A project manager is using the PERT technique to estimate the duration of a critical activity. The optimistic estimate is 10 days, and the pessimistic estimate is 22 days. What is the standard deviation for this activity?
The correct answer is 2 days. The standard deviation in PERT (Program Evaluation and Review Technique) is calculated using the formula: σ = (Pessimistic - Optimistic) / 6. In this case, we have:
σ = (22 - 10) / 6 = 12 / 6 = 2 days
This calculation is important because it helps project managers understand the variability in their estimates. A higher standard deviation indicates more uncertainty in the activity duration. In this case, a standard deviation of 2 days suggests a moderate level of uncertainty in the estimate.
The other answers are incorrect because they either use the wrong formula or misapply the given information. For example, 4 days would result from not dividing by 6, while 1 day and 3 days are arbitrary values that don't correspond to the correct calculation.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is PERT and why is it used in project management?
Open an interactive chat with Bash
How does the formula for standard deviation in PERT work?
Open an interactive chat with Bash
Why is dividing by 6 in the standard deviation formula important?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .