A project manager is using the Critical Path Method (CPM) to analyze a project schedule. They find that Activity X has an Early Start (ES) of 10 days and a Late Start (LS) of 15 days. What is the float for Activity X?
The correct answer is 5 days. In the Critical Path Method, float (also known as slack) is calculated as the difference between the Late Start (LS) and the Early Start (ES) of an activity. The formula for float is:
Float = LS - ES
In this case: Float = 15 days - 10 days = 5 days
Float represents the amount of time an activity can be delayed without affecting the project's overall duration. Activities with zero float are considered critical activities and form the critical path. Understanding float is crucial for project managers as it helps in prioritizing tasks and managing schedule constraints effectively.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the Critical Path Method (CPM)?
Open an interactive chat with Bash
What is float in project management?
Open an interactive chat with Bash
What does it mean for an activity to be on the critical path?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access