PMI Project Management Professional Practice Question
A project manager is using the Critical Path Method (CPM) to analyze a project schedule. They find that Activity X has an Early Start (ES) of 10 days and a Late Start (LS) of 15 days. What is the float for Activity X?
15 days
5 days
10 days
25 days