A project manager is using Earned Value Management to assess a project's performance. The Budget at Completion (BAC) is $500,000, and the current Cumulative Cost Performance Index (CPI) is 0.8. Assuming the current performance trend continues, what is the Estimate at Completion (EAC)?

  • $400,000

  • $550,000

  • $625,000

  • $500,000