PMI Project Management Professional Practice Question
A project manager is using Earned Value Management to assess a project's performance. The Budget at Completion (BAC) is $500,000, and the current Cumulative Cost Performance Index (CPI) is 0.8. Assuming the current performance trend continues, what is the Estimate at Completion (EAC)?
$400,000
$625,000
$500,000
$550,000