Project Management Professional Practice Question

A project manager is tasked with establishing a governance structure for a new project in a corporation where departments function independently but must comply with central corporate policies. What is the best course of action to align the project governance with corporate governance, while respecting departmental autonomy?

  • Design the project governance without regard to corporate governance, focusing solely on departmental needs.

  • Implement a standardized governance model used by the most successful department.

  • Adopt flexible governance, adjusting rules and processes as the project moves forward.

  • Conduct interviews with leaders from different departments to understand their alignment and challenges with corporate governance.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot