A project manager is reviewing the project's performance and needs to calculate the Estimate at Completion (EAC). The project has a Budget at Completion (BAC) of $500,000, and the current Cost Performance Index (CPI) is 0.8. Which of the following represents the most likely EAC assuming the current performance trend continues?
$625,000
$550,000
$500,000
$400,000