Project Management Professional Practice Question

A project manager is reviewing the performance of a $500,000 project. The plan was to have 50% of the work completed by this point. A recent assessment shows that only 40% of the work is actually complete, and the team has spent $220,000. Assuming the current cost performance trend will continue for the remainder of the project, what is the Estimate to Complete (ETC)?

  • $250,000

  • $280,000

  • $329,670

  • $300,000

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot