PMI Project Management Professional Practice Question
A project manager is reviewing the financial status of a project. The Estimate at Completion (EAC) is $250,000, and the Actual Cost (AC) to date is $150,000. What is the Estimate to Complete (ETC) for this project?
$100,000
$250,000
$400,000
$150,000