A project manager is reviewing the financial status of a project. The Estimate at Completion (EAC) is $250,000, and the Actual Cost (AC) to date is $150,000. What is the Estimate to Complete (ETC) for this project?

  • $150,000

  • $250,000

  • $100,000

  • $400,000