A project manager is preparing to showcase the value derived from the completed phases of a project. Which of the following would be the most effective way to evaluate and demonstrate the incremental value delivered to the stakeholders?
Comparing project deliverables with the initial value proposition.
Presenting the total project cost spent to date compared to the budget.
Listing the project's completed activities and tasks.
Describing the technical specifications of the project deliverables.