A project manager is performing a qualitative risk analysis and has identified the following four risks. Using the risk score (Probability x Impact), which of these risks should be prioritized the highest?
To determine the highest priority risk, calculate the risk score for each option by multiplying its probability by its impact.
Risk A: 0.2 x 0.8 = 0.16
Risk B: 0.4 x 0.5 = 0.20
Risk C: 0.7 x 0.2 = 0.14
Risk D: 0.9 x 0.1 = 0.09
Risk B has the highest score (0.20), and therefore, it should be prioritized the highest. This process of calculating and comparing risk scores is a key part of qualitative risk analysis, allowing the project team to focus its attention and resources on the most significant threats and opportunities.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is qualitative risk analysis in project management?
Open an interactive chat with Bash
Why is the risk score calculated as Probability x Impact?
Open an interactive chat with Bash
What happens after determining the highest-priority risk?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .