Project Management Professional Practice Question

A project manager is overseeing the development of a new financial software application. Midway through the project, the company announces a merger with another firm, which will introduce new regulatory compliance standards and a different set of stakeholders. To proactively manage this change, what is the project manager's most appropriate initial action?

  • Conduct an impact analysis to determine how the merger will affect the project's scope, stakeholders, and requirements.

  • Pause all project activities until the merger is fully completed and the new organizational structure is stable.

  • Immediately request additional funding to accommodate any potential changes from the merger.

  • Transfer leadership of the compliance-related tasks to the incoming team from the merged company.

Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot