PMI Project Management Professional Practice Question
A project manager is nearing the end of a project. What is the BEST action to take to ensure the project or phase is closed properly?
Conduct a final project performance report review and obtain formal acceptance of the project deliverables from the customer.
Archive all project documents.
Release all project team members and inform stakeholders that the project is completed.
Begin the next project.