A project manager is leading a virtual team with members from various countries. One team member consistently misses deadlines and appears disengaged during video conferences. Which of the following actions should the project manager take first to address this issue?

  • Discuss the issue with the entire team during the next video conference

  • Set clear expectations for all team members regarding deadlines and participation

  • Provide cultural sensitivity training to the entire team

  • Schedule a one-on-one meeting with the team member to discuss their challenges and cultural background